China's Datang to delay maintenance schedule of coal-based PP plant

China's Datang to delay maintenance schedule of coal-based PP plant

Title

Available in

Market sources reported that Datang Duolun Coal Chemical Corporation has delayed the turnaround schedule of its coal-based PP unit for another week to 17 September 2017.

Based in Inner Mongolia, China, the company has a No. 1 and No. 2 coal-based PP line each with a production capacity of 230,000 ton/year. The units initially were being planned for a 40-days scheduled maintenance on 10 September 2017.